We are pleased to inform you that as of 30 May 2010,
the project accomplishment is 82.35%. Tower A and B topped-off already at roof deck level. Ongoing works includes
installation of mechanical riser, installation and testing of water, fire protection, and sanitary lines, tile works, waterproofing works, installation of gypsum board drop ceiling
and granite lavatory counter top, spraycrete wall application, installation of aluminum windows and dry wall partitioning, electrical roughing-ins and ducting works.
Exterior painting substantially complete while interior painting is on progress for both Towers.
|