We are pleased to inform you that as of 30 May 2010, the project accomplishment is 82.35%. Tower A and B topped-off already at roof deck level. Ongoing works includes installation of mechanical riser, installation and testing of water, fire protection, and sanitary lines, tile works, waterproofing works, installation of gypsum board drop ceiling and granite lavatory counter top, spraycrete wall application, installation of aluminum windows and dry wall partitioning, electrical roughing-ins and ducting works. Exterior painting substantially complete while interior painting is on progress for both Towers.


Construction Report As Of 30 May 2010
  Excavation Works
100.00%
Completed
  Civil / Architectural Works
86.00%
On Schedule
  Mechanical Works
80.00%
On Schedule
  Electrical Works
68.00%
On Schedule
  Sanitary / Plumbing Works
81.00%
On Schedule
  Fire Protection Works
78.00%
On Schedule
  Painting Works
78.00%
On Schedule
  Aluminum & Glass Works
78.00%
On Schedule
  Elevator Works
82.00%
On Schedule

     