Cityplace Logo




We are pleased to inform you that as of 15 December 2011, the project accomplishment for the Twin Tower @ City Place is 93.59%. Ongoing work includes testing and cleaning of aluminum windows, final application of interior paintings,ceiling works and installation of: fixtures at T&B, baseboard for inside units, kitchen cabinet & bedroom closet, main door, wood planks, lighting @ hallway, water lines and breaker units. Retouching of punch listed items is also ongoing. Turn over of unit's to owner is also development for Tower A & B. The project is on progress with accordance to its schedule.

Construction Report As Of 15 December 2011
Excavation Works 100.00% Completed
Civil / Architectural Works 96.00% On Schedule
Mechanical Works 92.10% On Schedule
Electrical Works 92.30% On Schedule
Sanitary / Plumbing Works 92.25% On Schedule
Fire Protection Works 91.50% On Schedule
Painting Works 91.10% On Schedule
Aluminum & Glass Works 97.90% On Schedule
Elevator Works 93.10% On Schedule